|
Assessment of Project Benefits and Risks
Benefits:
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Risk Assessment Scale | ||
| Severity of Risk Impact | Probability of Risk Occurring | Overall Risk Level |
| High negative impact to project | Highly likely to occur | High |
| High negative impact to project | Medium likely to occur | High |
| High negative impact to project | Not likely to occur | Medium / Low |
| Medium negative impact to project | Highly likely to occur | Medium |
| Medium negative impact to project | Medium likely to occur | Medium / Low |
| Medium negative impact to project | Not likely to occur | Low |
| Low negative impact to project | Highly likely to occur | Low |
| Low negative impact to project | Medium likely to occur | Low |
| Low negative impact to project | Not likely to occur | Low |
3. For each high-level risk that you identified, create a risk response plan. There are five major responses to a risk - leave it, monitor it, avoid it, move it to a third party or mitigate it. Your plan should include steps to respond to the risk, including the people who are assigned, completion dates and periodic review dates to monitor progress.
4. Evaluate the medium-level risks to determine if the impact is severe enough that they should have a risk mitigation plan created for them as well. If the impact is severe enough, put together a risk response plan for them as well.
5. Look at any low risk items, and see whether they should be listed as assumptions. In this way you recognize that there is a potential for problems, but because the risk is low, you are 'assuming' that the condition will not occur.
6. Move the activities associated with the risk plans to the Project Work Plan. Moving the activities to the work plan should help ensure that the work is actually completed and keeps the work plan the primary focus of all work planning and monitoring.
7. The project manager needs to monitor the risk plans to ensure they are being executed successfully. If it looks like the risk is not being mitigated successfully, new risk plan activities should be added.
8. The project manager also needs to periodically evaluate risks throughout the project based on current circumstances. New risks may arise as the project is unfolding and some risks that were not identified during the Define Project step may become visible at a later date. This ongoing risk evaluation should be performed on a regular basis, say monthly, or at the completion of major milestones.
This document presents:
A definition of what is to be considered a risk
A risk management process
A criteria for quantifying risks
A template for tracking risks
Many situations will arise that have a wide range of potential impacts to the successful implementation of a project. A risk is an undesirable situation which has both the likelihood of occurring and a potential consequence to the program’s success. Risk is limited to a potential future event and does not pertain to events that have already occurred.
A risk event is stated as an assumed reality and the anticipated consequence if that reality should occur. Good risk management begins with precise and comprehensive definition of a risk. The following table provides examples of poorly written and improved risk statements:
|
Poorly Written Risk Statements | Improved |
|
The current over-utilization of human resources in the organization |
Software programmers are not available as planned (assumed reality), thereby causing schedule impacts (anticipated consequence). |
|
Operating manuals should have a testing mechanism to ensure usability. |
Operating manuals are not usable (assumed reality) causing cost impacts (anticipated consequence). . |
|
The concern that not all technical glitches have been adequately resolved |
Significant defects may occur during final test (assumed reality), thereby causing schedule and cost impacts (anticipated consequence). |
|
The current over-utilization of human resources in our customer’s organization |
Customer does not have resources available to participate in the requirements-gathering activities (assumed reality). The project could be delayed by an additional 2 months of recovery time to capture missed requirements. (anticipated consequence). |
|
With poor documentation of the existing environment and no resources to improve the documentation, issues may surface during installation. |
The documentation of existing environment is incomplete and resources for further definition are unavailable, therefore issues affecting installation may be discovered on site (assumed reality). If discovery occurs on site during installation, the installation activities could be delayed by 2 weeks or have to be rescheduled. (anticipated consequence). |
|
Subcontractor’s experience level and their ability to perform is questionable. |
Subcontractor has no established track record in performing this type of activity and training is not in the subcontractor plan (assumed reality). The quality of the integration effort may be degraded to the point of functionality loss in specific areas and delay implementation by 6 weeks. (anticipated consequence). |
Risk potentially affects the cost, quality or delivery dates of deliverables as well as the overall project.
Risk management concentrates on identification and control of the areas or events that have a potential of causing unwanted change.
There are four key components of the Risk Management Process:
Risk Identification
Risk Quantification
Risk Response Development
Risk Tracking
Risk identification is an organized, thorough approach to finding real risks associated with a project. The focus should be on potential likely occurrences. Avoid creating highly unlikely scenarios, as this tends to reduce the effectiveness of planning for eventualities. Some ways of identifying risks include interviews with experts or prior projects of a similar nature, and determining events that may threaten project goals.
The quantification of risks is the activity of analyzing each risk and prioritizing the order in which they should be handled. The first step in the analysis process is to categorize the risks. The two factors considered in categorization are likelihood of occurrence and severity of consequence. The following tables define the categories for each factor.
Determining the likelihood of occurrence is a subjective process. It is based on the assessment team’s experience, judgement and past project histories. Likelihood is generally expressed as a probability percentage and must be more than 0 and less than 100. For the purposes of risk quantification, use the probability percentage to categorize the likelihood.
Likelihood:
|
If your probability percentage is… |
Then your likelihood category is … |
And is assigned a risk likelihood level of ... |
|
1% - 5% |
Not Likely |
1 |
|
6% - 16% |
Low Likelihood |
2 |
|
17% - 83% |
Likely |
3 |
|
84% - 94% |
Highly Likely |
4 |
|
95% - 99% |
Near Certainty |
5 |
Severity of consequence will be categorized using the following indicators: (Note: Approved baselines for both schedule and effort estimates must exist in order to quantify the impact.)
Severity of Consequence:
|
If the consequence of the risk is … |
Then it is considered ... |
And is assigned a consequence severity of ... |
|
minimal |
Very Low |
1 |
|
·
same technical approach, · Schedule impact < 5%, · Budget increase < 5% |
Low |
2 |
|
· initiate workarounds, · Schedule impact < 10%; · Budget impact < 10% |
Moderate |
3 |
|
· unacceptable but workarounds available, critical path affected, · Schedule impact > 10%; · Budget impact > 10% |
High |
4 |
|
· unacceptable; no alternatives exist · Schedule impact > 15%; · Budget impact > 15% |
Very High |
5 |
After the risks have been categorized, the project manager will use these factors to determine the potential risk impact. Now the project manager has sufficient information to prioritize the risks.
Once the risk has been categorized and prioritized, the project manager and other appropriate parties (usually determined by type and nature of the risk) can begin to develop the response to that particular risk. The primary goal in most risk responses is to reduce the negative impact of a risk from a higher quantification level to a lower one. Responses may take several forms, but two of the most common are avoidance and control.
In many risk situations, the risk may be due to one of several alternative scenarios. In this case, the project manager must determine if the potential benefit of a chosen path justifies the associated risk. If the benefit is not sufficiently high or the risk is too great, then one of the alternative paths should be considered. This approach is called risk avoidance because by eliminating the most risky path, the associated consequences have been avoided.
Risk control, or mitigation, represents the most common approach to risk response. In this approach, a course of action is defined which reduces the impact or reduces the probability of risk occurrence. A project manager approaches this strategy using reviews, risk reduction milestones, fallback positions and other management strategies. These strategies may involve inclusion of risk activities and tasks into the work breakdown structure (WBS) and thus into the project schedule. But, regardless, the risk response activities must be tracked and monitored.
The risks identified having a likelihood of occurrence less than 3 or a consequence of severity less than 3 are usually not tracked at the Director Review level. These risks are tracked at the project level, and are with in the Project Manager’s prerogative to resolve.
Risks with likelihood and consequences of 3 or greater are tracked as follows:
All IC project managers will report risks using this process and common format. (Get URL address for IC0003 Risk Worksheet template & procedures IC PAL.)
Risk management documents are to reside in the project notebook in a common share on a server accessible by the project team.
Risk management activities are reported to the project’s steering committee on an interval as defined in the project statement (002)
As risks are identified or as they are being worked, it will sometimes require the active involvement of the IC Director. The criteria for determining director-level involvement varies, therefore it is best to check with your immediate manager to determine if your project falls under this requirement. When the risks of your project have been reduced to lower levels of likelihood and consequence, director involvement may no longer be required. This decision will be at the discretion of the IC Director.
We have not identified a meaningful metric to monitor and improve this process.
Risk Number: 01
Risk Title: Cost Allocation
Team: Process Improvement
Team Leader: < leader >
Release: N/A
Origination Date:
June 2001
Report Date: July 2001
Risk Statement: In order to meet the requirement of completing this year the cost allocation had to increase from the customer agreed to 5% to 10%. Customers have not agreed to the increase.
Quantify the Risk:
|
|
Place ‘o’ for original risk | |||||
|
L | 5 |
|
|
|
o c |
|
4 |
|
|
|
|
| |
3 |
|
|
|
|
| |
2 |
|
|
|
|
| |
1 |
|
|
|
|
| |
|
|
|
1 |
2 |
3 |
4 |
5 |
|
Severity |
|||||
Risk Reduction Plan:
Action/Event |
Date |
Success Criteria | Risk Level if Successful |
Comments | |
|
Planned |
Actual | ||||
|
Educate customers to the value of SEI/CMM. Work closely with customers to balance project and improvement goals
|
6/2001 |
8/2001 |
Customer agrees to increase SEI-CMM allocation to 5%. |
1 |
Customers have expressed concern about increasing SEI-CMM allocation above 5%.
|